© 2024 88.9 KETR
Public Radio for Northeast Texas
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

Minor installation remains in construction of new school

An image from Claycomb Associates Architects show installed display cases at the secondary corridor.
www.ssisd.net
An image from Claycomb Associates Architects show installed display cases at the secondary corridor.

SULPHUR SPRINGS - The new Sulphur Springs Middle School is now about 85 percent complete and should be ready for move in by the summer vacation. 

The School Board heard a report from architects this week. Only minor items remain to be done such as interior aluminum framing, bleachers and acoustic panels. 

The 160,000 square foot facility got behind schedule late last year. The original completion date allowed for officials to begin moving by over the winter break.